<div dir="ltr"><div>Week 5 of the Engineering 120 project is complete.</div><div><br></div><div>This week (Week 5), we completed
framing and plumbing rough in and started electrical rough in and installation of overhead mechanical components.
</div><div><br></div><div>Next week (Week 6), we intend to continue mechanical and electrical rough in and begin hanging drywall.</div><div><br></div><div>This project is currently projected to complete in mid-December 2019.</div><div><br></div><div>If you have questions, concerns, or would like more information, please contact:</div><div><br></div><div><b>Kara Peterson, Project Manager </b></div><div><b>cell: (619) 459-7477</b></div><div><b>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></b></div><div><b><br></b></div><div><b>Brian Smith, Construction Manager</b></div><div><b>cell: (916) 690-6982</b></div><div><b>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b></div><div><br></div><div><br></div><div><div><img src="cid:ii_k1mo0sj08" alt="Capture8.PNG" width="1071" height="533" style="margin-right: 0px;"></div></div><div><br></div><div><div dir="ltr" class="gmail_signature" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div><div><img src="cid:ii_k1mog49q9" alt="Capture1.jpg" width="541" height="562"><div><img src="cid:ii_k1mog4a910" alt="Capture2.jpg" width="536" height="562"><div><img src="cid:ii_k1mog4ag11" alt="Capture3.jpg" width="536" height="397" style="margin-right: 0px;"><br></div></div></div></div><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif"><br></span></b></div><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><font color="#999999"><a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></font></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div><div>___________________________________________________________ <br></div><div><br></div><div class="gmail_quote"><div dir="ltr" class="gmail_attr">From: <strong class="gmail_sendername" dir="auto">Kara Peterson</strong> <span dir="auto"><<a href="mailto:kara.peterson@sdsu.edu">kara.peterson@sdsu.edu</a>></span><br>Date: Fri, Oct 4, 2019 at 4:00 PM<br>Subject: Engineering 120 Project - Week 4 Update and Expected Impacts<br>To: <<a href="mailto:faculty@engineering.sdsu.edu">faculty@engineering.sdsu.edu</a>>, <<a href="mailto:staff@engineering.sdsu.edu">staff@engineering.sdsu.edu</a>>, Kara Peterson <<a href="mailto:kara.peterson@sdsu.edu">kara.peterson@sdsu.edu</a>><br></div><br><div dir="ltr"><div>Week 4 of the Engineering 120 project is complete.</div><div><br></div><div>This week (Week 4), we completed domestic water lines tie-in and replacement of the waste line (sawcutting, waste line replacement, rebar doweling, and concrete patch back).</div><div><br></div><div>Next week (Week 5), we intend to complete framing and rough in of mechanical, electrical, and plumbing; and start installation of overhead mechanical components.</div><div><b><br></b></div><div><b>We anticipate noise impacts from the framing work, so this work is scheduled to take place during early morning hours (2:00 AM - 8:00 AM) on Monday (10/07/19), Tuesday (10/08/19), Wednesday (10/09/19), Thursday (10/10/19), and Friday (10/11/19).</b></div><div><br></div><div>If you have questions, concerns, or would like more information, please contact:</div><div><br></div><div><b>Kara Peterson, Project Manager </b></div><div><b>cell: (619) 459-7477</b></div><div><b>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></b></div><div><b><br></b></div><div><b>Brian Smith, Construction Manager</b></div><div><b>cell: (916) 690-6982</b></div><div><b>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b></div><div><br></div><div><div dir="ltr" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><a href="mailto:kara.peterson@sdsu.edu" target="_blank"><font color="#999999">kara.peterson@sdsu.edu</font></a></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div><div>___________________________________________________________ <br></div><div class="gmail_quote"><div dir="ltr" class="gmail_attr"><br></div><div dir="ltr" class="gmail_attr">From: <strong class="gmail_sendername" dir="auto">Kara Peterson</strong> <span dir="auto"><<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>></span><br>Date: Wed, Oct 2, 2019 at 5:09 PM<br>Subject: Engineering 120 Project - Concrete Pour This Friday (10/04/19)<br>To: <<a href="mailto:faculty@engineering.sdsu.edu" target="_blank">faculty@engineering.sdsu.edu</a>>, <<a href="mailto:staff@engineering.sdsu.edu" target="_blank">staff@engineering.sdsu.edu</a>>, Kara Peterson <<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>> <br></div><br><div dir="ltr"><div class="gmail_quote"><div dir="ltr">The sawcutting for the new waste line is complete. <div><br></div><div>We currently have <b>concrete pour ("patch back" to fill in open trenches) scheduled for this Friday (10/04/19) from 10:00 am to 1:00 pm.</b><div><br></div><div>Anticipated impacts for this activity are <b>intermittent noise and vibration</b>, similar to trash collection. The concrete truck will be in front of the northeast building canopy and entrance during the pour, but building access will not be affected.</div><div><br></div><div>If you have questions, concerns, or would like more information now or during this activity, please contact:</div><div><br></div><div><div><div><b>Kara Peterson, Project Manager </b></div><div><b>cell: (619) 459-7477</b></div><div><b>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></b></div><div><b><br></b></div><div><b>Brian Smith, Construction Manager</b></div><div><b>cell: (916) 690-6982</b></div><div><b>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b></div></div><div><div dir="ltr" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif"><br></span></b></div><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><a href="mailto:kara.peterson@sdsu.edu" target="_blank"><font color="#999999">kara.peterson@sdsu.edu</font></a></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div><div class="gmail_quote"><div dir="ltr" class="gmail_attr">___________________________________________________________ </div><div dir="ltr" class="gmail_attr"><br>From: <strong class="gmail_sendername" dir="auto">Kara Peterson</strong> <span dir="auto"><<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>></span><br>Date: Fri, Sep 27, 2019 at 4:45 PM<br>Subject: Engineering 120 Project - Week 3 Update and Expected Impacts<br>To: <<a href="mailto:faculty@engineering.sdsu.edu" target="_blank">faculty@engineering.sdsu.edu</a>>, <<a href="mailto:staff@engineering.sdsu.edu" target="_blank">staff@engineering.sdsu.edu</a>>, Kara Peterson <<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>><br></div><br><div dir="ltr">Week 3 of the Engineering 120 project is complete.<div><br></div><div>This week (Week 3) we discovered a couple of <b>existing conditions that will have schedule and logistics impacts:</b></div><div><br></div><div><i><b>1) Waste Line Replacement:</b></i></div><div>The underground cast iron waste line (c. 1950s) is corroded and will now be replaced. </div><div>We will be performing <b>additional sawcutting to create additional trenches in the concrete slab during overnight work (10:00 pm to 6:00 am shift) on Monday (09/30) and Tuesday (10/1) next week (Week 4). </b></div><div><b>Noise and vibration will occur during this overnight sawcutting work (similar to Week 2 of the project).</b></div><div>When sawcutting is complete, the existing cast iron waste line will be removed and replaced with PVC pipe. </div><div>This work is currently expected to <b>add about one week to the project schedule.</b></div><div><div><br></div></div><div><i><b>2) Fire Rating Corrections:</b></i></div><div>The existing partition walls in the project space will need extensive rework to extend to the building deck and provide the required fire rating. </div><div>This work will likely add time to the project schedule, and may have associated noise impacts. These impacts will be communicated in a future update as this scope develops.</div><div><br></div><div>This week (Week 3), we completed:<br></div><div>- planned demolition;</div><div>- underground electrical;</div><div>- relocation of an electrical panel.</div><div><br></div><div>Next week (Week 4), we plan to:</div><div><b>- sawcut and demolish concrete during overnight work on Monday (09/30) and Tuesday (10/1) in order to replace the cast iron waste line;</b></div><div><b><font color="#000000">- shut down building water and air from 10:00 pm on Tuesday, 10/1 to 6:00 am on Wednesday, 10/2, as communicated in prior notices;</font></b></div><div>- replace the cast iron waste line with PVC; </div><div>- coordinate inspection of the new waste line.</div><div><br></div><div>During the <b>end of next week (Week 4) or beginning of Week 5 (week of 10/7), we will patch back the concrete removed in order to replace the waste line. </b></div><div><b>Delivery of the new concrete will likely present a couple of hours of noise and vibration.</b> We will make every effort to coordinate and receive delivery in early morning hours (before 8:00 am) to mitigate this impact. </div><div><br></div><div><div>If you have questions, concerns, or would like more information, please contact:</div><div><br></div><div><b>Kara Peterson, Project Manager </b></div><div><b>cell: (619) 459-7477</b></div><div><b>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></b></div><div><b><br></b></div><div><b>Brian Smith, Construction Manager</b></div><div><b>cell: (916) 690-6982</b></div><div><b>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b></div></div><div><br></div><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div><div><div dir="ltr" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><font color="#999999"><a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></font></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div><div class="gmail_quote"><div dir="ltr" class="gmail_attr">___________________________________________________________</div><div dir="ltr" class="gmail_attr"><br>From: <strong class="gmail_sendername" dir="auto">Kara Peterson</strong> <span dir="auto"><<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>></span><br>Date: Mon, Sep 23, 2019 at 11:34 AM<br>Subject: Engineering 120 Project - Update and Expected Impacts<br>To: <<a href="mailto:faculty@engineering.sdsu.edu" target="_blank">faculty@engineering.sdsu.edu</a>>, <<a href="mailto:staff@engineering.sdsu.edu" target="_blank">staff@engineering.sdsu.edu</a>><br></div><br><div dir="ltr">Week 2 of the Engineering 120 project is complete:<br><br>Last week (Week 2), we completed demolition and concrete cutting and removal.<br><br>This week (Week 3), we are back to daytime work. <div>We plan to install underground plumbing and electrical at the beginning of the week, and patch back concrete in floor trenches at the end of the week.<br><br>We've learned that the Building does not currently have capability to isolate/localize domestic water or air shutdowns:<div>Thus, looking ahead to <b>next week (Week 4): on Tuesday, October 1, we intend to shutoff domestic water and compressed air to the entire Engineering Building, so that we may tie in the new spaces to Building utilities.</b></div><div>The shut down will occur <b>during night work, between the hours of 10:00 pm on Tuesday, October 1 and 6:00 am on Wednesday, October 2.</b></div><div><b>If your research or instruction will be affected by this overnight shutdown, please contact Kara Peterson at (619) 459-7477.<br></b><br>If you have questions, concerns, or would like more information, please contact:<br><br><b>Kara Peterson, Project Manager <br>cell: (619) 459-7477<br>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a><br><br>Brian Smith, Construction Manager<br>cell: (916) 690-6982<br>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b><div><b><br></b><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div><div><div><div dir="ltr" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><a href="mailto:kara.peterson@sdsu.edu" target="_blank"><font color="#999999">kara.peterson@sdsu.edu</font></a></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div><div dir="ltr" class="gmail_attr">___________________________________________________________</div><div class="gmail_quote"><div dir="ltr" class="gmail_attr"><br>From: <strong class="gmail_sendername" dir="auto">Kara Peterson</strong> <span dir="auto"><<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>></span><br>Date: Fri, Sep 13, 2019 at 4:45 PM<br>Subject: Engineering 120 Project - Update and Expected Impacts<br>To: <<a href="mailto:faculty@engineering.sdsu.edu" target="_blank">faculty@engineering.sdsu.edu</a>>, <<a href="mailto:staff@engineering.sdsu.edu" target="_blank">staff@engineering.sdsu.edu</a>><br></div><br><br><div dir="ltr"><div>The Engineering 120 project (buildout of three new research labs in the former E120 space) started on Wednesday.</div><div><br></div><div>This week, we completed moving and surplus, performed abatement and demolition, and set up site fencing. </div><div><br></div><div>Next week, we intend to continue and complete demolition and begin and complete concrete cutting. </div><div><b>We anticipate noise and vibration impacts for the concrete work, so work is scheduled to take place overnight </b><b>from 10:00 pm - 6:00 am </b><b>on Tuesday (09/17), Wednesday (09/18), and Thursday (09/20).</b></div><div><br></div><div><b>During night work on Wednesday (09/18), we intend to shutoff water to the 120 space.</b> </div><div><b>We anticipate this shutoff will be localized</b> to the 120 space only and will not affect the building, however, we will know more on Monday (09/16).</div><div><b>If a shutdown to building water is needed, it will occur during night work on Wednesday, and another email notice with specific details will follow this one on Monday, 09/16.</b></div><div><br></div><div>If you have questions, concerns, or would like more information, please contact:</div><div><br></div><div><b>Kara Peterson, Project Manager </b></div><div><b>cell: (619) 459-7477</b></div><div><b>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></b></div><div><b><br></b></div><div><b>Brian Smith, Construction Manager</b></div><div><b>cell: (916) 690-6982</b></div><div><b>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b></div><div><br></div><div><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div></div><div><div><div dir="ltr" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><a href="mailto:kara.peterson@sdsu.edu" target="_blank"><font color="#999999">kara.peterson@sdsu.edu</font></a></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div></div></div>
</div></div></div></div></div></div></div>
</div></div></div>
</div></div></div></div>
</div></div>
</div></div>
</div></div>