<div dir="ltr">Week 3 of the Engineering 120 project is complete.<div><br></div><div>This week (Week 3) we discovered a couple of <b>existing conditions that will have schedule and logistics impacts:</b></div><div><br></div><div><i><b>1) Waste Line Replacement:</b></i></div><div>The underground cast iron waste line (c. 1950s) is corroded and will now be replaced. </div><div>We will be performing <b>additional sawcutting to create additional trenches in the concrete slab during overnight work (10:00 pm to 6:00 am shift) on Monday (09/30) and Tuesday (10/1) next week (Week 4). </b></div><div><b>Noise and vibration will occur during this overnight sawcutting work (similar to Week 2 of the project).</b></div><div>When sawcutting is complete, the existing cast iron waste line will be removed and replaced with PVC pipe. </div><div>This work is currently expected to <b>add about one week to the project schedule.</b></div><div><br></div><div><font size="1">photo of existing cast iron pipe:</font></div><div><div><img src="cid:ii_k12qkwbf11" alt="image.png" width="512" height="370" style="margin-right: 0px;"><br></div></div><div><br></div><div><i><b>2) Fire Rating Corrections:</b></i></div><div>The existing partition walls in the project space will need extensive rework to extend to the building deck and provide the required fire rating. </div><div>This work will likely add time to the project schedule, and may have associated noise impacts. These impacts will be communicated in a future update as this scope develops.</div><div><br></div><div><font size="1">photo of existing partial-height wall and deck:</font></div><div><div><img src="cid:ii_k12r8hjg12" alt="Capture.JPG" width="514" height="368" style="margin-right: 0px;"><br></div></div><div><br></div><div>This week (Week 3), we completed:<br></div><div>- planned demolition;</div><div>- underground electrical;</div><div>- relocation of an electrical panel.</div><div><br></div><div>Next week (Week 4), we plan to:</div><div><b>- sawcut and demolish concrete during overnight work on Monday (09/30) and Tuesday (10/1) in order to replace the cast iron waste line;</b></div><div><b><font color="#000000">- shut down building water and air from 10:00 pm on Tuesday, 10/1 to 6:00 am on Wednesday, 10/2, as communicated in prior notices;</font></b></div><div>- replace the cast iron waste line with PVC; </div><div>- coordinate inspection of the new waste line.</div><div><br></div><div>During the <b>end of next week (Week 4) or beginning of Week 5 (week of 10/7), we will patch back the concrete removed in order to replace the waste line. </b></div><div><b>Delivery of the new concrete will likely present a couple of hours of noise and vibration.</b> We will make every effort to coordinate and receive delivery in early morning hours (before 8:00 am) to mitigate this impact.  </div><div><br></div><div><div>If you have questions, concerns, or would like more information, please contact:</div><div><br></div><div><b>Kara Peterson, Project Manager </b></div><div><b>cell: (619) 459-7477</b></div><div><b>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></b></div><div><b><br></b></div><div><b>Brian Smith, Construction Manager</b></div><div><b>cell: (916) 690-6982</b></div><div><b>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b></div></div><div><br></div><div><br></div><div><div><img src="cid:ii_k12pufzo10" alt="image.png" width="1212" height="643" style="margin-right: 0px;"><br></div></div><div><br clear="all"><div><div dir="ltr" class="m_-8840017425097137926gmail_signature" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><font color="#999999"><a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></font></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div><div class="gmail_quote"><div dir="ltr" class="gmail_attr">___________________________________________________________</div><div dir="ltr" class="gmail_attr"><br>From: <strong class="gmail_sendername" dir="auto">Kara Peterson</strong> <span dir="auto"><<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>></span><br>Date: Mon, Sep 23, 2019 at 11:34 AM<br>Subject: Engineering 120 Project - Update and Expected Impacts<br>To:  <<a href="mailto:faculty@engineering.sdsu.edu" target="_blank">faculty@engineering.sdsu.edu</a>>,  <<a href="mailto:staff@engineering.sdsu.edu" target="_blank">staff@engineering.sdsu.edu</a>><br></div><br><div dir="ltr">Week 2 of the Engineering 120 project is complete:<br><br>Last week (Week 2), we completed demolition and concrete cutting and removal.<br><br>This week (Week 3), we are back to daytime work. <div>We plan to install underground plumbing and electrical at the beginning of the week, and patch back concrete in floor trenches at the end of the week.<br><br>We've learned that the Building does not currently have capability to isolate/localize domestic water or air shutdowns:<div>Thus, looking ahead to <b>next week (Week 4): on Tuesday, October 1, we intend to shutoff domestic water and compressed air to the entire Engineering Building, so that we may tie in the new spaces to Building utilities.</b></div><div>The shut down will occur <b>during night work, between the hours of 10:00 pm on Tuesday, October 1 and 6:00 am on Wednesday, October 2.</b></div><div><b>If your research or instruction will be affected by this overnight shutdown, please contact Kara Peterson at (619) 459-7477.<br></b><br>If you have questions, concerns, or would like more information, please contact:<br><br><b>Kara Peterson, Project Manager <br>cell: (619) 459-7477<br>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a><br><br>Brian Smith, Construction Manager<br>cell: (916) 690-6982<br>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b><div><b><br></b><div><b><br></b></div><div><div><img src="cid:ii_k0wq2cmr4" alt="image.png" width="562" height="326" style="margin-right: 0px;"><br></div><div><br></div><div><div><img src="cid:ii_k0wqnj775" alt="Capture.PNG" width="203" height="194" style="margin-right: 0px;"><div><div><img src="cid:ii_k0wqnj807" alt="Capture3.PNG" width="204" height="214" style="margin-right: 0px;"><div><img src="cid:ii_k0wqnj888" alt="Capture4.PNG" width="204" height="265" style="margin-right: 0px;"><div><br></div></div></div></div></div></div><div><div><div dir="ltr" class="m_-8840017425097137926m_4607125654879459305m_-7946770829587903364m_-2053183303626137896gmail_signature" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><a href="mailto:kara.peterson@sdsu.edu" target="_blank"><font color="#999999">kara.peterson@sdsu.edu</font></a></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div><div dir="ltr" class="gmail_attr">___________________________________________________________</div><div class="gmail_quote"><div dir="ltr" class="gmail_attr"><br>From: <strong class="gmail_sendername" dir="auto">Kara Peterson</strong> <span dir="auto"><<a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a>></span><br>Date: Fri, Sep 13, 2019 at 4:45 PM<br>Subject: Engineering 120 Project - Update and Expected Impacts<br>To:  <<a href="mailto:faculty@engineering.sdsu.edu" target="_blank">faculty@engineering.sdsu.edu</a>>,  <<a href="mailto:staff@engineering.sdsu.edu" target="_blank">staff@engineering.sdsu.edu</a>><br></div><br><br><div dir="ltr"><div>The Engineering 120 project (buildout of three new research labs in the former E120 space) started on Wednesday.</div><div><br></div><div>This week, we completed moving and surplus, performed abatement and demolition, and set up site fencing. </div><div><br></div><div>Next week, we intend to continue and complete demolition and begin and complete concrete cutting. </div><div><b>We anticipate noise and vibration impacts for the concrete work, so work is scheduled to take place overnight </b><b>from 10:00 pm - 6:00 am </b><b>on Tuesday (09/17), Wednesday (09/18), and Thursday (09/20).</b></div><div><br></div><div><b>During night work on Wednesday (09/18), we intend to shutoff water to the 120 space.</b> </div><div><b>We anticipate this shutoff will be localized</b> to the 120 space only and will not affect the building, however, we will know more on Monday (09/16).</div><div><b>If a shutdown to building water is needed, it will occur during night work on Wednesday, and another email notice with specific details will follow this one on Monday, 09/16.</b></div><div><br></div><div>If you have questions, concerns, or would like more information, please contact:</div><div><br></div><div><b>Kara Peterson, Project Manager </b></div><div><b>cell: (619) 459-7477</b></div><div><b>email: <a href="mailto:kara.peterson@sdsu.edu" target="_blank">kara.peterson@sdsu.edu</a></b></div><div><b><br></b></div><div><b>Brian Smith, Construction Manager</b></div><div><b>cell: (916) 690-6982</b></div><div><b>email: <a href="mailto:brian@thebarriecompany.com" target="_blank">brian@thebarriecompany.com</a></b></div><div><br></div><div><div><img src="cid:ii_k0iq81fj0" alt="image.png" width="562" height="286" style="margin-right: 0px;"><br></div></div><div><br></div><div><div><img src="cid:ii_k0iraydd2" alt="Capture1.PNG" width="189" height="230" style="margin-right: 0px;"><br></div><div><br></div></div><div><div><div dir="ltr" class="m_-8840017425097137926m_4607125654879459305m_-7946770829587903364m_-2053183303626137896m_-1956994942632486721m_-8368071026426115764gmail_signature" data-smartmail="gmail_signature"><div dir="ltr"><div><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div dir="ltr"><div><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Kara Peterson, </span></b><b style="color:rgb(68,68,68)"><span style="font-family:Arial,sans-serif">Design Administrator</span></b><br></div><div dir="ltr"><blockquote style="margin:0px 0px 0px 40px;border:none;padding:0px"></blockquote><font color="#999999"><span style="font-size:9pt;font-family:Arial,sans-serif">San Diego State University</span><span style="font-family:Arial,sans-serif;font-size:12px">│</span><span style="font-family:Arial,sans-serif;font-size:9pt">Project Management</span></font></div><div dir="ltr"><font face="Arial, sans-serif" color="#999999"><span style="font-size:12px">5500 Campanile Drive, San Diego, CA 92182</span></font><div><font color="#999999"><span style="font-family:Arial,sans-serif;font-size:12px">6</span><span style="font-family:Arial,sans-serif;font-size:12px">19-594-6930 (o)</span><span style="font-family:Arial,sans-serif;font-size:12px">│619-459-7477 (c) </span></font></div><div><span style="font-family:Arial,sans-serif;font-size:9pt"><a href="mailto:kara.peterson@sdsu.edu" target="_blank"><font color="#999999">kara.peterson@sdsu.edu</font></a></span></div></div></div></div></div></div></div></div></div></div></div></div></div></div></div></div>
</div></div></div></div></div></div></div>
</div></div></div>