[Faculty] Noise Impacts: Engineering Building Lab Renovations Project

Andrea Rivas amrivas at sdsu.edu
Mon Jan 6 15:24:01 PST 2020


All,

This week we will be performing some demolish activities that will have
very high noise levels. This work will include saw cutting and concrete
chipping. We have scheduled this work for overnight hours to minimize the
impacts on building occupants. This work is scheduled as follows:

*Day 1*

*Start-* Wednesday 1/8/2020 start time 11:59 PM will be working 8 hours

*End-* Thursday 1/9/2020 end time 8:00AM



*Day 2*

*Start-* Thursday 1/9/2020 start time 11:59 PM will be working 8 hours

*End- *Friday 1/10/2020 end time 8:00AM



Please let me know if you have any questions or concerns regarding the
impacts of this work.


Thanks,
*Andrea M. Rivas│Construction Administrator*

San Diego State University│Project Management
5500 Campanile Drive, San Diego, CA 92182-1401
858.229.1925│amrivas at sdsu.edu
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://engineering.sdsu.edu/pipermail/faculty/attachments/20200106/866885dc/attachment.html>


More information about the Faculty mailing list